Completion of a life cycle cost (LCC) analysis requires expenditures for each
year of the project for calculating net present value (NPV). This requires estimating when things will
fail and the cost of the failures. A
Weibull database is helpful for selecting:
• shape factor beta (b tells about the failure mode) and
•
characteristic life eta (h tells about the durability).
The Weibull statistics tell how components fail. Failure costs follow the failures. You need
failure costs for the appropriate year to produce NPV details. You can also download an Excel worksheet for
computing NPV from this website.
Failures in early years are highly priced in NPV terms. Failures in later years are lower priced because of discounted values. All the following examples use a discount rate = 12%, project time span of 20 years, and a 38% tax provision for calculating the NPVs. Out-of-pocket expenditures refer to the first 20 years which is a typical project life.
Figure 1 produces a NPV = -$2,992 based on an out-of-pocket expenditure of $17,698.

Figure 1 shows the rhythms of replacement.
The replacement rhythms make waves of cost over the years for this wear
out failure mode. Expenditures deferred
to later years have strong, favorable, effects on NPV because of the discount
factors; whereas expenditures early in the project life are included at almost
current values which are very costly. Of
course the costs are driven by the failures, and Table 1 shows the details.

You can find the annual costs to include in life cycle cost NPV spreadsheets
by use of simple
Notice in Table 1 the first failure takes ~13 years to accumulate which is equal to 91.8% of the Weibull CDF. The second and third failures each take ~9 years which is not surprising since the calculated mean time to failure is 8.998 years for b = 3.5 and h = 10 years. The cumulative failures are shown in Table 1 with red numbers for failures near whole numbers.
Figure 2 with a b = 1.8, the NPV = -$3,680 based on an out-of-pocket expenditure of $19,157.

Figure 2’s replacement rhythms are not obvious because of the smaller beta value. Table 2 shows the failure costs.

Notice in Table 2 the first failure takes 12 years to accumulate which is 75% of the Weibull CDF. The second and third failures each take ~9 years which is not surprising since the calculated mean time to failure is 8.89 years for b = 1.8 and h = 10 years. The cumulative failures are shown in Table 2 with red numbers for failures near whole numbers.
Figure 3 shows the costs to be used each year for a chance failure mode with b = 1. Frequently this is a simplification decision (i.e., b = 1) on many life cycle cost sheets (unfortunately this decision takes major hits against NPV early in the life of the project).
Figure 3 produces a NPV = -$4,633 based on an out-of-pocket expenditure of $20,035.

When b = 1 and h = 10 years, this describes the exponential type, random failure and the mean time to failure is equal to eta (i.e., 10 years). As you can see from the costs curve we have 1/10 chance for failure each year, i.e., (1/10)*$10,000 = $1000 annual exposure. Detailed results of the simulation, regarding failures is shown in Table 3.

It’s easy to see that failures are occurring every 10 years in the simplified model of chance failures which is equal to 63.2% of the Weibull CDF. The simulated numbers for cost are ±0.2% of the expected value of $1000.
Figure 4 shows the costs to be used each year for the Weibull statistic with b = 0.7. These infant mortality failure modes (i.e., b < 1) incur high costs in the early years where expenditures carry a high value. Thus the NPV is worse than other conditions in Figure 1-3.
Figure 4 produces a NPV = -$5,374 with an out-of-pocket expenditure of $20,386.

The early high cost failures from infant mortality have major cost impact on NPV. The failure details and cost numbers are shown in Table 4 with the first failure accumulating in 8+ years.

The first failure occurs in 8 years which is 57.5% of the Weibull CDF, the second failure 12 years later, and the third failure is also 12 years later.
These four examples show:
1.
how to find failure costs for each project year with different failure
modes
2.
how early failure costs are killers for NPV
3.
the need for Weibull failure statistics to be able to find failures and
costs
4.
why it’s important to know how equipment will live and die to get
correct cost profiles by year
In summary, here is a comparison of these examples for repair when broken:

Figure 1’s results are the least negative and thus the preferred case. The least preferred case is shown in Figure 4 and Table 4.
You can find other LCC resources on this website:
1. Find Annual Cost For Life Cycle Cost Calculations With Planned Replacements
2. Optimizing Equipment Reliability Data for End-Users and Equipment Suppliers.
4. Life Cycle Cost & Reliability for Process Equipment
5. Life Cycle Cost And Good Practices
6. How to Justify Machinery Improvements Using Reliability Engineering Principles
8. How To Justify Equipment Improvements Using Life Cycle Cost and Reliability Principles
9. Reliability Issues From A Management Perspective
11. Life Cycle Cost Analysis—Who Does What?
12. Reliability And Life Cycle Cost
Return to the list of problems by clicking here.
Refer to the caveats on the Problem
Of The Month Page about the limitations of the solution above.
Maybe you have a better idea on how to solve the problem. Maybe you find where
I've screwed-up the solution and you can point out my errors as you check my
calculations. E-mail your comments, criticism, and corrections to: Paul
Barringer by
clicking
here. Return
to the top of this problem.
You can download a PDF copy of this Problem Of The Month by clicking here. By the way, the tables are readable in the PDF file.
Return to Barringer
& Associates, Inc. homepage